
Case Study
This is a contract management failure, not a contractor-bashing exercise.
In a nutshell, an HVAC contractor was engaged to replace a Fan Coil Unit (FCU). The contractor submitted a price, received a purchase order, and commenced the works. On paper, it was a small and straightforward job. In reality, it became a costly and avoidable failure driven by a flawed scope of works and poor contract governance at the very beginning of the process.
The lesson is not about behaviour after the fact — it is about what was written, what was assumed, and what was never questioned.
A scope of works document for the FCU replacement was issued by the Building Manager. On the surface, this appeared reasonable. However, the scope had not actually been authored by the Building Manager.
It had originally been written by the incumbent HVAC subcontractor — a contractor with long-standing site knowledge and a deep understanding of how the building operated.
That original scope relied heavily on assumptions:
The incumbent contractor had included wording such as “disconnect and reconnect services”, fully aware of what this meant in practice. Their price allowed for the time, labour, coordination, and commissioning effort required.
However, their price was deemed too high.
The Building Manager, a capable and well-intentioned individual employed by the owner, copied the incumbent’s scope onto company letterhead and issued it to alternative contractors for pricing.
This is a common industry practice and, in many cases, a reasonable strategy. It can promote competition, keep incumbents honest, and deliver cost savings.
In this case, however, it proved disastrous.
By reissuing the scope without challenge or clarification, several things happened simultaneously:
The incumbent had written a scope that functioned as a memory prompt.
The new contractor read it as a literal instruction set.
Those are not the same thing.
A new HVAC contractor submitted a lower price and was awarded the work. The Building Manager reasonably believed he had achieved a saving while introducing competitive tension on site.
From the contractor’s perspective, he priced exactly what was written — nothing more and nothing less.
This is where the distinction between technical scope and operational impact became critical.
The contractor shut off the water to replace the FCU.
He did not notify anyone.
He did not know he was required to.
As a result, a server room lost cooling and shut down. The consequences were immediate and severe. The colour of the air was predictable.
This was not contractor negligence — it was a missing requirement.
There was no isolation strategy, no notification protocol, and no critical services mapping in the scope.
Once the FCU was installed, commissioning began.
Each issue was addressed — but none had been allowed for.
The new HVAC contractor had not priced:
These became variations.
The final cost more than doubled the original contract value and exceeded the incumbent contractor’s original price.
The lowest price became the most expensive outcome.
But none of this is the real point.
This was not a failure of:
It was a contract management failure.
Specifically:
A scope of works is not merely a technical description.
It is a risk allocation document.
In this case, risk was accidentally transferred to the owner.
Beyond cost, the scope failed to address:
The Building Manager, acting in good faith, exposed the owner to unnecessary operational and commercial risk by issuing a scope that was incomplete but appeared adequate.
We could debate for hours:
None of that changes the core issue.
The initial document was flawed.
It should never have been used for pricing.
Everything that followed was predictable, avoidable, and expensive.
This is not an argument against competitive tendering.
It is an argument for competent scope authorship and contract governance, especially on “small” jobs — because small jobs fail quietly until they don’t.

A routine Fan Coil Unit (FCU) replacement resulted in operational disruption and costs exceeding original expectations. The issue did not arise from contractor performance, but from a flawed scope of works that relied on implicit site knowledge and was reissued without governance review.
The incident highlights a systemic governance gap in how scopes of works are authored, reviewed, and issued for competitive tendering — particularly for small works.
The failure occurred before works commenced, due to:
The scope of works functioned as a technical description rather than a risk allocation document.